Mathematics 4

Starting in Spring 2025, I have been photographing the construction of the University of Waterloo's Mathematics 4 (M4) building as it has progressed. I also have some other pictures from before then. I will update this page as construction progresses.

October 2024: Before

Early bridge closure from the Davis Centre (DC) side
Early bridge closure from the Mathematics & Computer Building (MC) side
Opened gates prior to construction
Inside the DC-MC bridge

MC-DC bridge gone (December 2024 to January 2025)

Demolition as seen from the now-closed DC Cafeteria
Empty construction site in January 2025

April 2025

Mostly clear construction site, April 2025

June 2025

Site still appears mostly empty, June 2025
Foundation work, June 2025
Foundation work, June 2025

July 2025

Start of construction from the MC-Student Life Centre (SLC) bridge
A closer look at the construction, July 2025
Start of construction at sunrise, July 2025
A closer look at the construction site from the previous picture.

August 2025

Concrete columns and the elevator shaft rose up, August 2025.
Another perspective from the MC-SLC bridge.

September 2025

Start of steel construction as seen from MC-Student Life Centre (SLC) bridge
A closer look at the steel construction, September 2025

October 2025

Mostly complete steel construction, October 2025.
A closer look at the steel beams, October 2025.
East-side perspective on the steel construction, October 2025
Mostly complete steel construction, October 2025

November 2025

I visited the University of Waterloo twice in November 2025 and took pictures of M4 during both visits.

Mostly complete steel construction, November 2025.
Ruffled slabs on the beams, November 2025.
East-side perspective on the steel construction, November 2025
Ruffled steel plates covering most floors on the west side of the building, November 2025.
Eastern extent of the ruffled steel plates, November 2025.
East-side perspective showing frame mostly done, November 2025

December 2025

Not much progress was made between my late November and mid-December visits.

Northeast side showing mostly completed frame, December 2025.
Further steel frame progress on the east side, December 2025.
Northeast extent of steel frame, December 2025
Frame near MC building complete with steel ruffle plates partly done, December 2025



Last updated: 01/01/2026